Contract Value for Sangdo Stadium Apartment Project Increases to KRW 573.6 Billion (from KRW 555.6 Billion)
- Disclosure amendment: Contract value for Sangdo Stadium housing association apartment new construction project, originally signed in Nov 2023, increased from KRW 555,622,000,000 to KRW 573,576,000,000 (increase of KRW 17,954,000,000 or 3.2%)
- Contract period: 46 months from actual construction start date 2024-04-01 (ending 2028-01-31)
- Project scale: 11 buildings, B5-F35, 2,002 households and ancillary facilities in Sangdo-dong, Dongjak-gu, Seoul
- Contract amount represents 5.67% of latest annual revenue (KRW 10,122,930,837,450)