Contract Amount for Gangwon Power Tunnel Project Revised Up by 1.8%


  • Correction of single sales/supply contract: contract amount increased by 1.8% from KRW 78.77B to KRW 80.56B (approx. +KRW 1.8B).
  • Sales ratio revised up from 4.41% to 4.51% (based on 2022 consolidated revenue of KRW 1.79T).
  • Counterparty: Korea Electric Power Corporation (KEPCO); project location in Jeongseon, Gangwon; contract period July 2023 – Nov 2027.
  • Amount reflects the company's 80% share; project includes Shield TBM, total power tunnel length 4,004m.
  • Other conditions (advance payment, progress payment) and potential schedule changes remain unchanged.